Main Street / Blush Hill Update Aug. 6-13

Downtown paving was completed in record time. Final details will be addressed this week as the project moves toward completion. Click for more details.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street / Blush Hill Update July 30-Aug. 6

Buckle up for the final push toward completion for the Main Street project. Two weeks of paving is scheduled to begin Aug. 2. No street parking during paving. Alternating one-lane traffic. Click for more details.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street / Blush Hill Update July 23-30

Here’s the latest on Main Street and Blush Hill road construction projects that will impact downtown travelers, local residents, and visitors to the Waterbury Reservoir boat launch.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street/Blush Hill Update July 16-23

Here’s the latest on Main Street and Blush Hill road construction projects that will impact local residents and visitors to the Waterbury Reservoir boat launch.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street / Blush Hill Update July 9-16

Here’s the latest on Main Street work and a new project on Blush Hill that will impact local residents and visitors to the Waterbury Reservoir boat launch in the coming weeks.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street/Blush Hill Update June 24-July 2

Here’s the latest on Main Street work and a new paving project started on Blush Hill that will impact local residents and visitors to the Waterbury Reservoir boat launch in the coming weeks.

Read More
Waterbury Roundabout Waterbury Roundabout

Main St. Construction | June 4-June 11

Work on Stowe Street’s dry bridge is finished. Notice new information kiosks under construction. Sidewalk work continues. Click to read more.

Read More
Waterbury Roundabout Waterbury Roundabout

Main St. Construction | May 28-June 4

Work to refurbish the dry bridge on lower Stowe Street continues through June 2. All road and sidewalk work will stop by noon Friday through Monday for the Memorial Day weekend. Click to read more.

Read More
Waterbury Roundabout Waterbury Roundabout

Main St. Construction | May 21-28

The dry bridge on Stowe Street will get a facelift starting this week. All work stops by noon Friday for the Memorial Day weekend. Click to read more.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street Construction | May 15-21

Sidewalk construction continues along Main Street. Work is expected on the Dry Bridge on Lower Stowe Street. Foundations for information kiosks will be installed in several locations. Click to read more.

Read More
Lisa Scagliotti Lisa Scagliotti

Main Street Construction | May 8-14

Sidewalk construction continues along Main Street. Work is expected on the Dry Bridge on Lower Stowe Street. Foundations for information kiosks will be installed in several locations. Click to read more.

Read More
Julia Bailey-Wells Julia Bailey-Wells

Main Street Construction | April 30-May 7

Special Note: In addition to the Main Street project, repairs are scheduled for Reservoir Road leading to the Waterbury Reservoir State Park in Waterbury Center starting Monday, May 3. The road will be closed to the public for a week. The parking area above the gate at the top of the road will also be closed during this time.  

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street Construction | April 26-30

Items to complete over the next few months include: sidewalks, walkways, installation of new lampposts, landscaping, signage, a final layer of pavement, final line striping.

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street Construction | Dec. 17-31

Some minor electrical work remains to be wrapped up through the rest of this month. Expect to see one-lane alternating traffic patterns this week while lights and signals are being worked on. Flaggers also will be present where activities are taking place. 

Read More
Waterbury Roundabout Waterbury Roundabout

Main Street Construction | Dec. 12-18

Work on the new streetlights will be taking place all week from Dac Rowe Park to Park Row. The new mast arms and traffic signal at the Stowe Street-Main Street intersection will take place early this week pending weather conditions.  

Read More