Main St. Construction Update | June 11-June 18

OVERALL IMPACTS

  • Flaggers and pedestrian crossers will be present where construction is taking place. 

  • Watch for changing work locations and traffic patterns.

  •  Weekends are construction free!

Segment 1.  North Main Street between railroad bridge and Stowe Street

  • Work will continue to prep and install new concrete sidewalks and walkways.  Walkways and sidewalks will take a day or two to be able to walk on but areas that cross driveways can take up to 7 days before they can be driven on. 

  • There are four properties (odd-numbered) remaining on North Main Street that need new concrete sidewalks installed across their driveways. Property owners will be contacted in advance for timing.  Residents should communicate with workers if they are blocking a driveway so they can make accommodations. When new concrete is poured, vehicles will need to park off site for several days until the concrete has cured. Parking is available at the municipal office building and library. Neighbors are encouraged to coordinate to share parking.

  • Work continues on installing an informational kiosk at the Bidwell Lane-Stowe Street intersection. 

  • Drainage structures in the roadway are being raised to prepare for paving in July.

Segment 2.  South Main Street between Stowe Street and Park Street

  • Sidewalks on the Pro Pig side of Elm Street and the Elm Street parking lot will be back and functioning this week. 

  • Elm Street will be milled and prepped in order to pave it in the next week or two.  The exact schedule is dependent on availability of equipment and personnel.  This will result in approximately 4 days of heavy activity on Elm Street.  

  • Sidewalks and driveways will be cleaned up and opening along South Main between Stowe Street and the fire station on the fire station side of the road. 

  • Drainage structures in the roadway are being raised to prepare for paving in July.

  • Kiosk work continues near the former TD Bank parking lot. 

Segments 3 and 4 from Park Row to the end of the project  

  • Information kiosk installation continues at the corner of Park Row and South Main Street and the corner of Demeritt Place and South Main Street.  

  • Miscellaneous construction activity will be taking place. 

The work schedule is contingent on weather, equipment, supplies and a variety of circumstances. Get more information and sign up for updates at waterburyworks.com. Project contact is Barb Farr at 802-244-4300 or bfarr@waterburyvt.com