Main Street / Blush Hill Update July 9-16
BLUSH HILL
Work has begun to mill pavement on Blush Hill Road in preparation for paving later this summer. The operation was interrupted by a machine breakdown but was expected to resume this week with equipment back in service. Milling will be followed by work on two culverts and ditches. Afterward, paving will be done along Blush Hill and on Lonesome Trail. Traffic will be limited to alternating single lanes during much of that work. Updates will be posted when the schedule is revised.
MAIN STREET
OVERALL IMPACTS
Clean-up on Main Street will take place the remainder of this week in preparation for the NQID parade and celebration on Saturday, July 10.
Flaggers and pedestrian crossers will be present where construction is taking place.
Construction activities will be taking place on the entire length of the project including side roads.
Segments 1 and 2: North Main Street between railroad bridge and Park Row
Work will continue to grade, seed and mulch areas by sidewalks and driveways that had been disturbed by the construction activities.
Drainage structures in the roadway are being raised to prepare for paving toward the end of July.
Remaining new street lamps will be installed from Dac Rowe Park to the fire station.
Reseeding as needed.
Segments 3 and 4 from Park Row to the end of the project
Drainage structures in the roadway are being raised to prepare for paving in July.
Healy Court will be graded and resurfaced where construction took place. Expect delays in access while this work happens.
Reseeding as needed.
The work schedule is contingent on weather, equipment, supplies and a variety of circumstances. Get more information and sign up for updates at waterburyworks.com. Project contact is Barb Farr at 802-244-4300 or bfarr@waterburyvt.com.