Main Street Construction Update | July 24 - 31

Construction activities are ongoing in all segments along Main Street and side roads. Flaggers and pedestrian crossers are present throughout. Expect traffic delays and one-way alternating traffic.

Between Dac Rowe Park and Stowe Street

Hydrant connections and water and sewer line service installations continue in this segment. Residents and businesses should have water on site for drinking, washing, and flushing while work is ongoing in this area. Expect traffic delays. Driveways will have temporary closures as excavation is done. Temporary parking is available at the municipal offices and library.  

Between Stowe Street and Park Street

Final drainage excavation will take place between Bargain Boutique and Waterbury Sports.  Businesses are open. Expect traffic delays. Conduit installation will continue from the Fire Station to Elm Street. Curbing prep and installation will be done along South Main St. between Park Street and Foundry Street.

From Park Row to the end of the project

Residential walkways will have concrete poured or paving done depending on what was there prior to construction.

MONTHLY PHOTO CONTEST

Submit Main Street construction photos by July 31 for the July photo contest. Send to bfarr@waterburyvt.com. The top three entries will get a free cone coupon from The Udder Guys ice cream tricycle cart. 

MORE INFO

To sign up for email updates or for questions, contact Community Transportation Liaison Barb Farr at 888-3810 or 244-4300, bfarr@waterburyvt.com. Much more detailed information including maps, project drawings, etc. online at waterburyworks.com.

Previous
Previous

Police issue description, warning regarding escaped prison inmate with ties to Waterbury

Next
Next

Tools, equipment stolen from J.A. McDonald, Kingsbury contractor sites