Main Street Construction Update | Oct. 31 to Nov. 6
Overall impacts
Paving: Expect delays the week of Nov. 2 due to paving throughout the project along Main Street, side streets and gravel sidewalks. This is due to a weather delay from last week.
Driveway, sidewalk, and walkway cleanup continues.
Flaggers and pedestrian crossers will be present in the construction areas.
Special Note: The Edward Farrar Utility District, the utility district for the village, has contracted with J.A. McDonald to replace a water line on lower Stowe Street between Main Street and Bidwell Lane. This is not part of the VTrans Main Street project.
Between Stowe Street and Park Street
Concrete sidewalk installation is planned between Waterbury Sports and Foundry Street and at the Main Street-Park Row intersection.
New street lighting will continue to be installed.
Town of Waterbury water line project on Stowe Street
Stowe Street may be closed for thru traffic on Monday, Nov. 2, for the new water line interconnection at the intersection with Main Street. Stowe Street businesses will be open.