Main Street / Blush Hill Update Aug. 27 - Sept. 3
BLUSH HILL
Due to rescheduling because of rainy weather, paving is now set to begin Tuesday, Sept. 7. Crews will begin with paving Lonesome Trail and then move to the Blush Hill Road portion of the project.
The work is contingent on weather and could be rescheduled if there is steady or heavy rain.
MAIN STREET
Work on Main Street is complete. Some remaining sidewalk work may be left to finish to replace concrete that didn’t cure properly in Segments 3 and 4.
Other repairs will be done soon to exterior features at some businesses that were affected by road and sidewalk construction. That work will not involve disruptions to traffic.